Frequently Asked Questions
System studies have shown a need to increase the transfer capacity on the current transmission system in this area. This increase would provide a generation outlet for the proposed 150 megawatt (MW) Merricourt Wind Farm. In addition, it may benefit future wind energy projects. This Project would, also, provide transmission grid reliability to MDU’s existing Wishek to Ellendale 230 kV transmission line.
MDU will follow the North Dakota regulatory process by applying for two approvals from the North Dakota Public Service Commission (PSC): a Certificate of Corridor Compatibility (N.D.C.C. Section 49-03) and a Route Permit (N.D. Admin Code 69-02). MDU is seeking a waiver from the PSC to file a combined Certificate of Corridor Compatibility and Route Permit. Additional approvals/permits from state agencies may be required, such as the North Dakota Department of Transportation. Other state agencies will be consulted including but not limited to the State Historical Society of North Dakota, North Dakota Game and Fish Department, North Dakota Parks and Recreation, and North Dakota State Water Commission.
The line will likely be constructed from wooden H-frame structures. Typical H-frame structures will be approximately 70-90 feet in height with an average span of approximately 800 feet and a maximum span of approximately 1,000 feet.
Some sections of the line may be double-circuited with an existing MDU transmission line requiring taller structures with shorter spans (approximately 500 feet) between structures.
Project construction is anticipated to begin in spring 2011 and be energized by fall 2011.
Once the permitting and environmental review work is complete, a preferred line route will be identified and easements will be acquired. A property survey will be performed to prepare plats describing the easements. An aerial survey will also be performed to obtain the topographic data required to design the line. After the design has determined the final pole locations, typical construction follows the steps listed below. During construction, all heavy equipment used will be driven within the easement right-of-way or approved access roads.
Typical Transmission Line Construction Steps:
- Survey structure locations and identify ingress and egress locations
- Auger the holes where the structures will be set
- Assemble the structure on the ground adjacent to the holes
- Lift structure, place in hole, and backfill with soil or crushed rock
- Sting wires
- Restore right-of-way
- Energize line
MDU will minimize impacts during construction of the transmission line by using existing public and private roads, where possible, and all construction equipment will follow the same two-track to ingress and egress the Project site. The total area that may be temporarily disturbed within the vicinity of each structure is expected to be confined to an area within the right-of-way of about 50-feet-wide by 50-feet-long
(2,500 ft or 0.06 acres).
No permanent access roads will be constructed for the Project; however, temporary construction access roads will be needed in some locations to access pole locations. Temporary construction access roads will utilize existing public and private roads where possible, and will be up to 20-feet-wide and located through disturbed uplands (e.g., farmed land) where no existing roads provide access.


